Project Management

4.      Project Cost Management

          Includes the process is estimating, budgeting, financing, managing, and controlling cost so that a project can be                      completed within the approved budget.

           i.        Plan Cost

                     a.      Inputs

                              i.        Project Charter

                             ii.       Project Management Plan

                            iii.     Project Documents from above

                            iv.     Enterprise Environmental Factors

                             v.       Organizational Assets

                     b.      Tools

                              i.        Expert Judgement

                             ii.       Data Analysis

                            iii.     Meetings

                     c.      Output

                              i.        Cost Management Plan

           ii.      Estimate Cost

                     a.      Inputs

                               i.        Project Charter

                              ii.       Project Management Plan

                             iii.     Project Documents from above

                             iv.     Enterprise Environmental Factors

                              v.       Organizational Assets

                     b.      Tools

                               i.        Expert Judgement

                               ii.       Parametric Estimating

                               iii.     Three-point Estimating

                               iv.     Project Management  Info

                                v.       Analogous Estimating

                               vi.     Bottom-up Estimating

                              vii.   Data Analysis

                             viii. Decision Making

                     c.      Output

                               i.        Cost Estimate

                              ii.       Basis of Estimate

                                         a.      How

                                         b.      Assumptions

                                         c.       Risk

                                         d.      Constraints

                             iii.       Project Documents Updates

           iii.    Determine Budget

                     a.      Input

                              i.        Project Charter

                             ii.       Project Management Plan

                            iii.     Project Documents from

                                      a.      Activity of Cost

                                      b.      Project Schedule

                            iv.     Business Documents

                             v.     Agreements

                            vi.     Enterprise Environmental Factors

                           vii.     Organizational Assets

                     b.      Tools

                              i.      Expert Judgment

                             ii.      Cost

                            iii.     Aggregations

                            iv.     Data Analysis

                             v.      Historical information review

                            vi.     Funding limit

                           vii.     Financing

                     c.      Output

                              i.        Cost Baseline

                              ii.       Project Funding requirements

                             iii.     Cost Estimate

                             iv.     Risk schedule

                             v.       Project Updates

          iv.      Control Cost

                     a.      Input

                              i.        Project Charter

                              ii.       Project Management Plan

                             iii.     Project Documents from above

                             iv.     Enterprise Environmental Factors

                              v.       Organizational Assets

                     b.      Tools

                               i.        Expert Judgement

                              ii.       Data Analysis

                             iii.     To-Complete Performance

                             iv.     Project Management Information System

                     c.      Output

                               i.        Work Performance

                              ii.       Cost Forecast

                             iii.     Change Request

                             iv.     Project Document Updates

 

 Earned Value Management

Earned Value vs Planned Value

Earned Value (EV)   is the budget allocated to each of the activities that have been completed at that point in time.

Planned Value (PV)   is the total of all work packages planned for project = Project Budget

 

Earned Value (EV) is compared to Planned Value (PV) to determine if the project is on track.

 

             Acronym                                  Term                                                                             Explanation

                 PV                                  Planned Value                                     Authorized budget assigned to scheduled work

                 EV                                   Earned Value                                       Worked performed in terms of budget authorized for work

                 AC                                  Actual Cost                                          Actual cost incurred in work performed

                 BAC                                Budget at Completion                      Budgeted amount for the total work

                 EAC                                Estimate at Completion                   Estimated total cost of project

                 ETC                                 Estimate to Complete                      Expected cost to finish all remaining project work

                 VAC                                Variance at Completion                   Projected budget surplus or deficit at end of project.

 

             Term                                                            Formula                                                            Interpretation

 Cost Variance (CV)                                            EV- AC                               Negative is over budget: positive is under budget

Schedule Variance (SV)                                      EV – PV                            Negative is behind schedule; positive is ahead of schedule

Cost Performance Index (CPI)                        EV/AC                               Worth of work gotten of every dollar

Schedule Performance Index (SPI)                 EV/PV                               Percentage progress made against plan rate

Calculations

Estimate at Completing (EAC)                       BAC/CPI                            Work performed at current CPI

AC + [(BAC-EV)/(CPI*SPI)]                                                                            Factorizing in both CPI and SPI

Estimate to Completion (ETC)                       EAC – AC                         Amount of cost from current to end

Variance at Completion (VAC)                       BAC – EAC                      Over budget or under budget

To Complete Performance Index (TCPI)        

·         (BAC – EV) / (BAC – AC)                            for managing to budget

·         (BAC – EV) / (EAC – AC)                            to manage to a specified value